New Garage

Day 1, laying out the footings for the new garage.
Footings dug, rebar and hardware cloth in place, ready for the cemet.
Cement truck stuck trying to back up to pour new garage floor.
I am supervising the new floor.
Carol watches the framing.
Sheathing with Celotex fiber board due to reconstruction of Irag induced shortage and cost of plywood.
Roof trusses arrive.
Trusses going up.

It is February and work stops for winter at an inappropriate stage of construction.

 

Building inspector determines that the header over the garage door does not meet code and must be replaced with a manufactured laminated wood header. We wait for this to be made and installed.

Garage door has been mounted and flagstone has been delivered.

Still waiting for the return of the building inspector before stucco can be applied.

To be continued...

Back